SB 165 - AS AMENDED BY THE SENATE

 

03/28/2019   1169s

2019 SESSION

19-1079

10/08

 

SENATE BILL 165

 

AN ACT relative to net energy metering by low-moderate income community solar projects.

 

SPONSORS: Sen. Feltes, Dist 15; Sen. Fuller Clark, Dist 21; Sen. Watters, Dist 4; Sen. Bradley, Dist 3; Sen. Hennessey, Dist 5; Rep. Moffett, Merr. 9; Rep. Oxenham, Sull. 1; Rep. Luneau, Merr. 10; Rep. Myler, Merr. 10

 

COMMITTEE: Energy and Natural Resources

 

─────────────────────────────────────────────────────────────────

 

ANALYSIS

 

This bill modifies the method for calculating net energy metering credits for low-moderate income community solar group host projects.

 

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

 

Explanation: Matter added to current law appears in bold italics.

Matter removed from current law appears [in brackets and struckthrough.]

Matter which is either (a) all new or (b) repealed and reenacted appears in regular type.

03/28/2019   1169s 19-1079

10/08

 

STATE OF NEW HAMPSHIRE

 

In the Year of Our Lord Two Thousand Nineteen

 

AN ACT relative to net energy metering by low-moderate income community solar projects.

 

Be it Enacted by the Senate and House of Representatives in General Court convened:

 

1  Short Title.  This act shall be known as the "Low-Income Community Solar Act of 2019."

  2  Net Energy Metering; Group Host; Community Solar.  Amend RSA 362-A:9, XIV(c) to read as follows:

(c)  Notwithstanding paragraph V, a group host shall be paid for its surplus generation at the end of each billing cycle at rates consistent with the credit the group host receives relative to its own net metering under either subparagraph IV(a) or (b) or alternative tariffs that may be applicable pursuant to paragraph XVI.  [Each group member of] Alternatively, a group host [for a low-moderate income community solar project, as defined in RSA 362-F:2, X-a,] may elect to receive credits on the customer electric bill for each member and the host[, provided that there shall be only one new project under this paragraph in each utility's service territory by December 31, 2019 with such projects available on a first-come, first-served basis], with the utility being allowed the most cost-effective method of doing so according to an amount or percentage specified for each member on PUC form 909.09 (Application to Register or Re-register as a Host), along with a 3 cent per kwh addition for low-moderate income community solar projects, as defined in RSA 362-F:2, X-a.  The commission shall report on the costs and benefits of [such projects] low-moderate income community solar projects, as defined in RSA 362-F:2, X-a on or before [December 31, 2019] June 1, 2020.  The commission shall authorize at least 2 new low-moderate income community solar projects, as defined in RSA 362-F:2, X-a, each year in each utility's service territory beginning January 1, 2020.  On an annual basis, for all group host systems except for residential systems with an interconnected capacity under 15 kilowatts, the electric distribution utility shall calculate a payment adjustment if the host's surplus generation for which it was paid is greater than the group's total electricity usage during the same time period.  The adjustment shall be such that the resulting compensation to the host for the amount that exceeded the group's total usage shall be at the utility's avoided cost or its default service rate in accordance with subparagraph V(b) or paragraph VI or alternative tariffs that may be applicable pursuant to paragraph XVI.  The utility shall pay or bill the host accordingly.  

3  Effective Date.  This act shall take effect 60 days after its passage.