Bill Text: HI HB2534 | 2024 | Regular Session | Introduced


Bill Title: Relating To Capital Improvement Projects For The Benefit Of The Thirty-fourth Representative District.

Spectrum: Partisan Bill (Democrat 1-0)

Status: (Introduced) 2024-01-26 - Referred to FIN, referral sheet 3 [HB2534 Detail]

Download: Hawaii-2024-HB2534-Introduced.html

HOUSE OF REPRESENTATIVES

H.B. NO.

2534

THIRTY-SECOND LEGISLATURE, 2024

 

STATE OF HAWAII

 

 

 

 

 

 

A BILL FOR AN ACT

 

 

relating to capital improvement projects for the benefit of THE Thirty-fourth REPRESENTATIVE DISTRICT.

 

 

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:

 


     SECTION 1.  The director of finance is authorized to issue general obligation bonds in the sum of $84,430,000 or so much thereof as may be necessary and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2024-2025 for the purpose of capital improvement projects for the thirty-fourth representative district, as follows:

1.   Momilani elementary and Pearl City high school joint integrated academy

     Plans, design, and equipment and appurtenances for a joint integrated academy for Momilani elementary school and Pearl City high school.

     Plans                        $2,500,000

     Design                      $40,000,000

     Equipment                    $2,000,000

          Total funding                    $44,500,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

2.   Momilani elementary school

     Design and construction for perimeter fencing and security improvements and all related work, including new and refurbishing work, repair and renovation, ground and site improvements.

     Design                          $50,000

     Construction                 $3,500,000

          Total funding                     $3,550,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

3.   Momilani elementary school

     Design and construction for renovation, resurfacing, and reflooring of the multi-purpose cafeteria.

     Design                          $50,000

     Construction                 $1,000,000

          Total funding                     $1,050,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

4.   Momilani elementary school

     Plans, design, and construction for the expansion, renovation and improvements, ground and site improvements for an administrative building.

     Plans                        $1,000,000

     Design                       $1,000,000

     Construction                $15,000,000

          Total funding                    $17,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

5.   Palisades elementary school

     Construction for an outdoor play court.

     Construction                 $5,500,000

          Total funding                     $5,500,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

6.   Pearl City elementary school

     Plans, design, construction, and equipment and appurtenances for slope stabilization for the hills on campus.

     Plans                           $10,000

     Design                          $10,000

     Construction                 $5,000,000

     Equipment                       $20,000

          Total funding                     $5,040,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

7.   Pearl City elementary school

     Plans, design, construction, and equipment and appurtenances to replace campus waterlines.

     Plans                           $10,000

     Design                          $10,000

     Construction                 $2,500,000

     Equipment                       $20,000

          Total funding                     $2,540,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

8.   Pearl City high school

     Design and construction to resurface tennis courts.

     Design                          $50,000

     Construction                   $600,000

          Total funding                       $650,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

9.   Pearl City high school

     Design, construction, and equipment and appurtenances to retrofit stadium lighting.

     Design                          $50,000

     Construction                   $300,000

     Equipment                      $150,000

          Total funding                       $500,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

10.  Pearl City high school

     Plans, design, construction, and equipment and appurtenances to retrofit and renovate A/B, C/D, and KLM elevators.

     Plans                           $50,000

     Design                         $200,000

     Construction                 $1,000,000

     Equipment                      $100,000

          Total funding                     $1,350,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

11.  Waiau elementary school

     Construction for the completion of electrical upgrade.

     Construction                   $500,000

          Total funding                       $500,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

12.  Waiau elementary school

     Plans, design, construction, and equipment and appurtenances for covered walkways for portables and sidewalks for safety and shelter.

     Plans                          $100,000

     Design                         $100,000

     Construction                 $2,000,000

     Equipment                       $50,000

          Total funding                     $2,250,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

     SECTION 2.  The appropriation made for the capital improvement projects authorized by this Act shall not lapse at the end of the fiscal year for which the appropriation is made; provided that all moneys from the appropriation unencumbered as of June 30, 2026, shall lapse as of that date.

     SECTION 3.  This Act shall take effect on July 1, 2024.

 

INTRODUCED BY:

_____________________________

 

 


 


 

Report Title:

CIP; Thirty-fourth Representative District; Appropriation

 

Description:

Appropriates funds for capital improvement projects in the thirty-fourth representative district.

 

 

 

The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.

feedback