Bill Text: HI HB2352 | 2022 | Regular Session | Introduced


Bill Title: Relating To Capital Improvement Projects For The Benefit Of The Forty-first Representative District.

Spectrum: Partisan Bill (Democrat 1-0)

Status: (Introduced - Dead) 2022-01-28 - Referred to FIN, referral sheet 3 [HB2352 Detail]

Download: Hawaii-2022-HB2352-Introduced.html

HOUSE OF REPRESENTATIVES

H.B. NO.

2352

THIRTY-FIRST LEGISLATURE, 2022

 

STATE OF HAWAII

 

 

 

 

 

 

A BILL FOR AN ACT

 

 

relating to capital improvement projects for the benefit of THE Forty-first REPRESENTATIVE DISTRICT.

 

 

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:

 


     SECTION 1.  The director of finance is authorized to issue general obligation bonds in the sum of $622,097,250 or so much thereof as may be necessary and the same sum or so much thereof as may be necessary is appropriated for fiscal year 2022-2023 for the purpose of capital improvement projects for the forty-first representative district, as follows:

1.   Saratoga Avenue electrical and communication infrastructure improvements in Kalaeloa, Oahu

     Construction for Saratoga Avenue electrical and communication infrastructure improvements in Kalaeloa, Oahu.

     Construction                $12,125,000

          Total funding                    $12,125,000

     The sum appropriated for this capital improvement project shall be expended by the department of business, economic development, and tourism.

2.   Barbers point elementary school, Oahu

     Design and construction for air conditioning for the entire school.

     Design                         $500,000

     Construction                 $4,500,000

          Total funding                     $5,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

3.   Barbers point elementary school, Oahu

     Design and construction for cafeteria restrooms.

     Design                         $150,000

     Construction                 $1,350,000

          Total funding                     $1,500,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

4.   East Kapolei high school, Oahu

     Plans, design, construction, and equipment for a new high school; ground and site improvements; and equipment and appurtenances.

     Plans                        $1,499,000

     Design                      $16,000,000

     Construction               $132,000,000

     Equipment                        $1,000

          Total funding                   $149,500,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

5.   East Kapolei middle school, Oahu

     Plans, design, construction, and equipment for a new middle school; ground and site improvements; and equipment and appurtenances.

     Plans                        $1,000,000

     Design                       $2,000,000

     Construction               $120,640,000

     Equipment                   $10,000,000

          Total funding                   $133,640,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

6.   Ewa beach elementary school, Oahu

     Construction for asphalt paving and parking lot.

     Construction                 $3,000,000

          Total funding                     $3,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

7.   Ewa beach elementary school, Oahu

     Plans and construction for covering of play courts and night lighting.

     Plans                          $500,000

     Construction                 $4,500,000

          Total funding                     $5,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

8.   Ewa beach performing arts center, Oahu

     Plans, land, design, construction, and equipment for phase one of a new performing arts center; ground and site improvements; and equipment and appurtenances.

     Plans                          $100,000

     Land                             $1,000

     Design                       $1,498,000

     Construction                $20,000,000

     Equipment                        $1,000

          Total funding                    $21,600,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

9.   Ewa Beach public library, Oahu

     Plans and design for a new public library.

     Plans                           $50,000

     Design                         $100,000

          Total funding                       $150,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

10.  Ilima intermediate school, Oahu

     Construction for concrete walkway.

     Construction                    $40,000

          Total funding                        $40,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

11.  Ilima intermediate school, Oahu

     Construction for renovation of cafeteria restroom.

     Construction                    $87,500

          Total funding                        $87,500

     The sum appropriated for this capital improvement project shall be expended by the department of education.

12.  Ilima intermediate school, Oahu

     Construction for replacement of cafeteria kitchen light fixture.

     Construction                    $40,000

          Total funding                        $40,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

13.  Ilima intermediate school, Oahu

     Construction for replacement of drains leaking from the second floor of D building.

     Construction                   $200,000

          Total funding                       $200,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

14.  Ilima intermediate school, Oahu

     Construction for replacement of exterior doors of R building (computer lab).

     Construction                    $26,000

          Total funding                        $26,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

15.  Ilima intermediate school, Oahu

     Construction for replacement of floor tiles in front office.

     Construction                   $400,000

          Total funding                       $400,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

16.  Ilima intermediate school, Oahu

     Construction for replacement of front of campus fence.

     Construction                   $120,000

          Total funding                       $120,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

17.  Ilima intermediate school, Oahu

     Construction for replacement of walkway behind C building with concrete.

     Construction                    $50,000

          Total funding                        $50,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

18.  Ilima intermediate school, Oahu

     Construction for reroofing of cafeteria.

     Construction                   $468,750

          Total funding                       $468,750

     The sum appropriated for this capital improvement project shall be expended by the department of education.

19.  Ilima intermediate school, Oahu

     Construction for small retaining wall located three feet behind D building.

     Construction                   $200,000

          Total funding                       $200,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

20.  Ilima intermediate school, Oahu

     Design and construction for sixth grade building.

     Design                      $10,000,000

     Construction                $25,000,000

          Total funding                    $35,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

21.  Ilima intermediate school, Oahu

     Plans and construction for campus-wide painting of the exterior building walls and remodeling and repainting of the interior of the cafeteria.

     Plans                          $500,000

     Construction                 $7,500,000

          Total funding                     $8,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

22.  Ilima intermediate school, Oahu

     Plans, design, and construction for cafetorium renovations.

     Plans                          $900,000

     Design                         $100,000

     Construction                 $4,000,000

          Total funding                     $5,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

23.  Ilima intermediate school, Oahu

     Plans, design, and construction for replacement of the existing fence and cattle gates at the front of the school with a reinforced wall and new gates; ground and site improvements.

     Plans                          $500,000

     Design                         $500,000

     Construction                 $7,000,000

          Total funding                     $8,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

24.  Iroquois point elementary school, Oahu

     Plans, design, and construction for a playground cover or awning.

     Plans                            $1,000

     Land                             $1,000

     Construction                    $48,000

          Total funding                        $50,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

25.  James Campbell high school, Oahu

     Design and construction for an athletic complex, including a new stadium; a new Title IX-compliant girls' athletic locker room; restroom facilities; ground and site improvements; and equipment and appurtenances, per master plan.

     Design                       $1,500,000

     Construction                $28,800,000

          Total funding                    $30,300,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

26.  Kapolei high school, Oahu

     Design and construction for a fine arts auditorium.

     Design                       $4,000,000

     Construction                $36,000,000

          Total funding                    $40,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

27.  Kapolei high school, Oahu

     Design and construction for a shelter in place (administration buildings B, D, G, H).

     Design                         $200,000

     Construction                 $1,300,000

          Total funding                     $1,500,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

28.  Kapolei high school, Oahu

     Design and construction for restrooms for portables.

     Design                         $100,000

     Construction                   $750,000

          Total funding                       $850,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

29.  Kapolei high school, Oahu

     Plans, design, and construction for new classroom building; ground and site improvements.

     Plans                        $1,000,000

     Design                       $2,000,000

     Construction                $37,000,000

          Total funding                    $40,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

30.  Kapolei middle school, Oahu

     Design and construction for a classroom building.

     Design                       $4,500,000

     Construction                $40,500,000

          Total funding                    $45,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

31.  Kapolei middle school, Oahu

     Design and construction for a shelter in place (library buildings A, C, E, F, G, H, I).

     Design                         $150,000

     Construction                 $1,600,000

          Total funding                     $1,750,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

32.  Kapolei middle school, Oahu

     Design and construction for restrooms for portables.

     Design                         $100,000

     Construction                   $750,000

          Total funding                       $850,000

     The sum appropriated for this capital improvement project shall be expended by the department of education.

33.  Fort Weaver road, Oahu

     Design and construction for Fort Weaver road, sidewalks, crosswalks, signals, and related signage.

     Design                       $1,600,000

     Construction                $20,000,000

          Total funding                    $21,600,000

     The sum appropriated for this capital improvement project shall be expended by the department of transportation.

34.  Fort Weaver road, Oahu

     Plans and construction for installation of additional traffic cameras along Fort Weaver road at the intersections of Keoneula boulevard, Papipi road, and Keaunui Drive and along Kapolei parkway.

     Plans                           $50,000

     Construction                   $500,000

          Total funding                       $550,000

     The sum appropriated for this capital improvement project shall be expended by the department of transportation.

35.  Fort Weaver road, Oahu

     Plans, design, and construction for a pedestrian bridge overpass for Ft. Weaver road near Child and Family Service; ground and site improvements.

     Plans                          $200,000

     Design                         $600,000

     Construction                 $3,700,000

          Total funding                     $4,500,000

     The sum appropriated for this capital improvement project shall be expended by the department of transportation.

36.  Fort Weaver road, Oahu

     Plans, design, and construction for widening of Fort Weaver road to add a third lane and sidewalks to Fort Weaver road in both directions from Geiger road to Keoneula boulevard; ground and site improvements.

     Plans                            $1,000

     Design                           $1,000

     Construction                $33,998,000

          Total funding                    $34,000,000

     The sum appropriated for this capital improvement project shall be expended by the department of transportation.

37.  Kalaeloa Enterprise street lighting project, Oahu

     Design and construction for the Kalaeloa Enterprise street lighting project.

     Design                         $400,000

     Construction                 $1,600,000

          Total funding                     $2,000,000

     The sum appropriated for this capital improvement project shall be expended by the Hawaii community development authority.

38.  University of Hawaii, west Oahu, Oahu

     Plans, design, and construction for campus improvements.

     Plans                        $1,000,000

     Design                       $1,000,000

     Construction                 $8,000,000

          Total funding                    $10,000,000

     The sum appropriated for this capital improvement project shall be expended by the university of Hawaii.

     SECTION 2.  The appropriation made for the capital improvement projects authorized by this Act shall not lapse at the end of the fiscal year for which the appropriation is made; provided that all moneys from the appropriation unencumbered as of June 30, 2024, shall lapse as of that date.

     SECTION 3.  This Act shall take effect on July 1, 2022.

 

INTRODUCED BY:

_____________________________

 

 


 


 

Report Title:

CIP; Forty-first Representative District; Appropriation

 

Description:

Appropriates funds for capital improvement projects in the forty-first representative district.

 

 

 

The summary description of legislation appearing on this page is for informational purposes only and is not legislation or evidence of legislative intent.

feedback