Bill Text: FL S1056 | 2010 | Regular Session | Comm Sub


Bill Title: Local Government Prompt Payment Act [CPSC]

Spectrum: Partisan Bill (Republican 1-0)

Status: (Introduced - Dead) 2010-04-27 - Placed on Special Order Calendar; Read 2nd time -SJ 00919; Amendment(s) adopted (495022, 482460) -SJ 00919; Substituted CS/HB 1157 -SJ 00919; Laid on Table, companion bill(s) passed, see CS/HB 1157 (Ch. 2010-111) -SJ 00919 [S1056 Detail]

Download: Florida-2010-S1056-Comm_Sub.html
 
       Florida Senate - 2010                      CS for CS for SB 1056 
        
       By the Committees on Judiciary; and Community Affairs; and 
       Senator Baker 
       590-05219A-10                                         20101056c2 
    1                        A bill to be entitled                       
    2         An act relating to the Local Government Prompt Payment 
    3         Act; amending s. 218.72, F.S.; revising definitions; 
    4         amending s. 218.735, F.S.; revising provisions 
    5         relating to the timely payment for purchases of 
    6         construction services; providing that a payment 
    7         request or invoice that is not rejected within a 
    8         certain time after an overdue notice is sent is deemed 
    9         accepted; requiring a local governmental entity to 
   10         identify in a construction contract the agent or 
   11         employee or facility or office to which a contractor 
   12         may submit its payment request or invoice; requiring 
   13         that an ordinance providing dispute resolution 
   14         procedures applicable to a construction contract be 
   15         referenced in the contract; requiring construction 
   16         contracts to specify a date for the delivery of a list 
   17         of items required to render complete, satisfactory, 
   18         and acceptable the construction services purchased by 
   19         a local governmental entity; providing for the 
   20         extension of the contract if the list of items 
   21         remaining to complete is not timely provided to the 
   22         contractor; specifying the time for paying any 
   23         remaining undisputed contract amount; amending s. 
   24         218.76, F.S.; revising provisions relating to the 
   25         resolution of disputes concerning an improper payment 
   26         request or invoice; providing that a local 
   27         governmental entity waives its objection in a payment 
   28         dispute if it fails to commence the dispute resolution 
   29         procedure within a certain time and after receiving 
   30         notice from the contractor; providing an effective 
   31         date. 
   32   
   33  Be It Enacted by the Legislature of the State of Florida: 
   34   
   35         Section 1. Section 218.72, Florida Statutes, is reordered 
   36  and amended to read: 
   37         218.72 Definitions.—As used in this part, the term: 
   38         (8)(1) “Proper invoice” means an invoice that which 
   39  conforms with all statutory requirements and with all 
   40  requirements that have been specified by the local governmental 
   41  entity to which the invoice is submitted. Such requirements must 
   42  be included in the contract for the project for which the 
   43  invoice is submitted. 
   44         (5)(2) “Local governmental entity” means a county or 
   45  municipal government, school board, school district, authority, 
   46  special taxing district, other political subdivision, or any 
   47  office, board, bureau, commission, department, branch, division, 
   48  or institution thereof. 
   49         (4)(3) “County” means a political subdivision of the state 
   50  established pursuant to s. 1, Art. VIII of the State 
   51  Constitution. 
   52         (6)(4) “Municipality” means a municipality created pursuant 
   53  to general or special law and metropolitan and consolidated 
   54  governments as provided in s. 6(e) and (f), Art. VIII of the 
   55  State Constitution. 
   56         (9)(5) “Purchase” means the purchase of goods, services, or 
   57  construction services; the purchase or lease of personal 
   58  property; or the lease of real property by a local governmental 
   59  entity. 
   60         (10)(6) “Vendor” means any person who sells goods or 
   61  services, sells or leases personal property, or leases real 
   62  property directly to a local governmental entity. The term 
   63  includes any person who provides waste hauling services to 
   64  residents or businesses located within the boundaries of a local 
   65  government pursuant to a contract or local ordinance. 
   66         (2)(7) “Construction services” means all labor, services, 
   67  and materials provided in connection with the construction, 
   68  alteration, repair, demolition, reconstruction, or any other 
   69  improvements to real property. 
   70         (7)(8) “Payment request” means a request for payment for 
   71  construction services which conforms with all statutory 
   72  requirements and with all requirements specified by the local 
   73  governmental entity to which the payment request is submitted. 
   74  Such requirements must be included in the contract for the 
   75  project for which payment is requested. 
   76         (1)(9) “Agent” means the project architect, project 
   77  engineer, or any other agency or person acting on behalf of the 
   78  local governmental entity. The agent who is required to review 
   79  invoices or payment requests must be identified in accordance 
   80  with s. 218.735(2). 
   81         (3)(10) “Contractor” or “provider of construction services” 
   82  means the any person who contracts directly with a local 
   83  governmental entity to provide construction services. 
   84         Section 2. Present subsections (8) and (9) of section 
   85  218.735, Florida Statutes, are redesignated as subsections (9) 
   86  and (10), respectively, and present subsections (1) through (7) 
   87  of that section are amended, to read: 
   88         218.735 Timely payment for purchases of construction 
   89  services.— 
   90         (1) The due date for payment for the purchase of 
   91  construction services by a local governmental entity is 
   92  determined as follows: 
   93         (a) If an agent must approve the payment request or invoice 
   94  before prior to the payment request or invoice is being 
   95  submitted to the local governmental entity, payment is due 25 
   96  business days after the date on which the payment request or 
   97  invoice is stamped as received as provided in s. 218.74(1). The 
   98  contractor may send the local government an overdue notice. If 
   99  the payment request or invoice is not rejected within 2 business 
  100  days after delivery of the overdue notice, the payment request 
  101  or invoice is deemed accepted, except for any portion that is 
  102  fraudulent or misleading. 
  103         (b) If an agent need not approve the payment request or 
  104  invoice which is submitted by the contractor, payment is due 20 
  105  business days after the date on which the payment request or 
  106  invoice is stamped as received as provided in s. 218.74(1). 
  107         (2) A local governmental entity shall identify the agent or 
  108  employee of the local governmental entity, or the facility or 
  109  office, to which the contractor may submit its payment request 
  110  or invoice. 
  111         (a) This requirement must be included in the contract 
  112  between the local governmental entity and contractor, or, as 
  113  required by the contract, must be provided by the local 
  114  governmental entity through a separate written notice within 10 
  115  days after the contract award. 
  116         (b) A contractor’s submission of a payment request or 
  117  invoice to the identified agent, employee, facility, or office 
  118  of the local governmental entity must be stamped as received as 
  119  provided in s. 218.74(1), and commences the time periods for 
  120  payment or rejection of a payment request or invoice as provided 
  121  in this subsection and subsection (3). 
  122         (3)(2)If a payment request or invoice does not meet the 
  123  contract requirements, the local governmental entity must may 
  124  reject the payment request or invoice within 20 business days 
  125  after the date on which the payment request or invoice is 
  126  stamped as received as provided in s. 218.74(1). The rejection 
  127  must be written and must specify the deficiency in the payment 
  128  request or invoice and the action necessary to make the payment 
  129  request or invoice proper. 
  130         (4)(3) If a payment request or an invoice is rejected under 
  131  subsection (3) (2) and the contractor submits a corrected 
  132  payment request or invoice that which corrects the deficiency 
  133  specified in writing by the local governmental entity, the 
  134  corrected payment request or invoice must be paid or rejected on 
  135  the later of: 
  136         (a) Ten business days after the date the corrected payment 
  137  request or invoice is stamped as received as provided in s. 
  138  218.74(1); or 
  139         (b) If the local governmental entity governing body is 
  140  required by ordinance, charter, or other law to approve or 
  141  reject the corrected payment request or invoice, the first 
  142  business day after the next regularly scheduled meeting of the 
  143  local governmental entity governing body held after the 
  144  corrected payment request or invoice is stamped as received as 
  145  provided in s. 218.74(1). 
  146         (5)(4) If a dispute between the local governmental entity 
  147  and the contractor cannot be resolved by the procedure in 
  148  subsection (4) (3), the dispute must be resolved in accordance 
  149  with the dispute resolution procedure prescribed in the 
  150  construction contract or in any applicable ordinance, which must 
  151  be referenced in the contract. In the absence of a prescribed 
  152  procedure, the dispute must be resolved by the procedure 
  153  specified in s. 218.76(2). 
  154         (6)(5) If a local governmental entity disputes a portion of 
  155  a payment request or an invoice, the undisputed portion shall be 
  156  paid timely, in accordance with subsection (1). 
  157         (7)(6)If When a contractor receives payment from a local 
  158  governmental entity for labor, services, or materials furnished 
  159  by subcontractors and suppliers hired by the contractor, the 
  160  contractor must shall remit payment due to those subcontractors 
  161  and suppliers within 10 days after the contractor’s receipt of 
  162  payment. If When a subcontractor receives payment from a 
  163  contractor for labor, services, or materials furnished by 
  164  subcontractors and suppliers hired by the subcontractor, the 
  165  subcontractor must shall remit payment due to those 
  166  subcontractors and suppliers within 7 days after the 
  167  subcontractor’s receipt of payment. This subsection does not 
  168  Nothing herein shall prohibit a contractor or subcontractor from 
  169  disputing, pursuant to the terms of the relevant contract, all 
  170  or any portion of a payment alleged to be due to another party 
  171  if the contractor or subcontractor notifies the party whose 
  172  payment is disputed, in writing, of the amount in dispute and 
  173  the actions required to cure the dispute. The contractor or 
  174  subcontractor must pay all undisputed amounts due within the 
  175  time limits imposed by this section. 
  176         (8)(7)(a) Each contract for construction services between a 
  177  local governmental entity and a contractor must provide for the 
  178  development of a single list of items required to render 
  179  complete, satisfactory, and acceptable the construction services 
  180  purchased by the local governmental entity. 
  181         (a) The contract must specify the process for developing 
  182  the development of the list, including the responsibilities of 
  183  the local governmental entity and the contractor in developing 
  184  and reviewing the list and a reasonable time for developing the 
  185  list, as follows: 
  186         1. For construction projects having an estimated cost of 
  187  Less than $10 million, within 30 calendar days after reaching 
  188  substantial completion of the construction services purchased as 
  189  defined in the contract, or, if not defined in the contract, 
  190  upon reaching beneficial occupancy or use; or 
  191         2. For construction projects having an estimated cost of 
  192  $10 million or more, within 30 calendar days, or, if unless 
  193  otherwise extended by contract, up to not to exceed 60 calendar 
  194  days, after reaching substantial completion of the construction 
  195  services purchased as defined in the contract, or, if not 
  196  defined in the contract, upon reaching beneficial occupancy or 
  197  use. 
  198         (b) The contract must also specify a date for the delivery 
  199  of the list of items, not to exceed 5 days after the list of 
  200  items has been developed and reviewed in accordance with the 
  201  time periods set forth in paragraph (a). 
  202         (c)(b) If the contract between the local governmental 
  203  entity and the contractor relates to the purchase of 
  204  construction services on more than one building or structure, or 
  205  involves a multiphased project, the contract must provide for 
  206  the development of a list of items required to render complete, 
  207  satisfactory, and acceptable all the construction services 
  208  purchased pursuant to the contract for each building, structure, 
  209  or phase of the project within the time limitations provided in 
  210  paragraph (a). 
  211         (d) The final contract completion date must be at least 30 
  212  days after the delivery of the list of items. If the list is not 
  213  provided to the contractor by the agreed date, the contract time 
  214  for completion must be extended by the number of days the local 
  215  governmental entity exceeded the delivery date. Damages may not 
  216  be assessed against a contractor for failing to complete a 
  217  project within the time required by the contract, unless the 
  218  contractor failed to complete the project within the contract 
  219  period as extended pursuant to this paragraph. 
  220         (e)(c) The failure to include any corrective work or 
  221  pending items not yet completed on the list developed pursuant 
  222  to this subsection does not alter the responsibility of the 
  223  contractor to complete all the construction services purchased 
  224  pursuant to the contract. 
  225         (f)(d) Upon completion of all items on the list, the 
  226  contractor may submit a payment request for all remaining 
  227  retainage withheld by the local governmental entity pursuant to 
  228  this section. If a good faith dispute exists as to whether one 
  229  or more items identified on the list have been completed 
  230  pursuant to the contract, the local governmental entity may 
  231  continue to withhold up to an amount not to exceed 150 percent 
  232  of the total costs to complete such items. 
  233         (g)(e) All items that require correction under the contract 
  234  and that are identified after the preparation and delivery of 
  235  the list remain the obligation of the contractor as defined by 
  236  the contract. 
  237         (h)(f) Warranty items or items not included in the list of 
  238  items may not affect the final payment of retainage as provided 
  239  in this section or as provided in the contract between the 
  240  contractor and its subcontractors and suppliers. 
  241         (i)(g) Retainage may not be held by a local governmental 
  242  entity or a contractor to secure payment of insurance premiums 
  243  under a consolidated insurance program or series of insurance 
  244  policies issued to a local governmental entity or a contractor 
  245  for a project or group of projects, and the final payment of 
  246  retainage as provided in this section may not be delayed pending 
  247  a final audit by the local governmental entity’s or contractor’s 
  248  insurance provider. 
  249         (j)(h) If a local governmental entity fails to comply with 
  250  its responsibilities to develop the list of items, including the 
  251  list required under paragraph (c), if applicable, (a) or 
  252  paragraph (b), as defined in the contract, within the time 
  253  limitations provided in paragraph (a), the contractor may submit 
  254  a payment request for all remaining retainage withheld by the 
  255  local governmental entity pursuant to this section. The payment 
  256  of any remaining undisputed contract amount, less any amount 
  257  withheld pursuant to the contract for incomplete or uncorrected 
  258  work, must be paid within 20 business days after receipt of a 
  259  proper invoice or payment request. If the local governmental 
  260  entity has provided written notice to the contractor specifying 
  261  the failure of the contractor to meet contract requirements in 
  262  developing the list of items to be completed, the local 
  263  governmental entity need not pay or process any payment request 
  264  for retainage if the contractor has, in whole or in part, failed 
  265  to cooperate with the local governmental entity in the 
  266  development of the list, or failed to perform its contractual 
  267  responsibilities, if any, with regard to the development of the 
  268  list, or if paragraph (9)(f) (8)(f) applies. 
  269         Section 3. Section 218.76, Florida Statutes, is amended to 
  270  read: 
  271         218.76 Improper payment request or invoice; resolution of 
  272  disputes.— 
  273         (1) If In any case in which an improper payment request or 
  274  invoice is submitted by a vendor, the local governmental entity 
  275  shall, within 10 days after the improper payment request or 
  276  invoice is received by it, notify the vendor, in writing, that 
  277  the payment request or invoice is improper and indicate what 
  278  corrective action on the part of the vendor is needed to make 
  279  the payment request or invoice proper. 
  280         (2) If In the event a dispute arises occurs between a 
  281  vendor and a local governmental entity concerning payment of a 
  282  payment request or an invoice, the dispute such disagreement 
  283  shall be finally determined by the local governmental entity 
  284  pursuant to as provided in this section. Each local governmental 
  285  entity shall establish a dispute resolution procedure 
  286  established to be followed by the local governmental entity in 
  287  cases of such disputes. 
  288         (a) The Such procedure must shall provide that proceedings 
  289  to resolve the dispute are shall be commenced within not later 
  290  than 45 days after the date on which the payment request or 
  291  proper invoice was received by the local governmental entity and 
  292  shall be concluded by final decision of the local governmental 
  293  entity within not later than 60 days after the date on which the 
  294  payment request or proper invoice was received by the local 
  295  governmental entity. Such procedures are shall not be subject to 
  296  chapter 120, and do such procedures shall not constitute an 
  297  administrative proceeding that which prohibits a court from 
  298  deciding de novo any action arising out of the dispute. If the 
  299  dispute is resolved in favor of the local governmental entity, 
  300  then interest charges shall begin to accrue 15 days after the 
  301  local governmental entity’s final decision. If the dispute is 
  302  resolved in favor of the vendor, then interest begins shall 
  303  begin to accrue as of the original date the payment became due. 
  304         (b) If the local governmental entity does not commence the 
  305  dispute resolution procedure within the time required, the 
  306  contractor may give written notice to the local governmental 
  307  entity of the failure to timely commence the dispute resolution 
  308  procedure. If the local governmental entity fails to commence 
  309  the dispute resolution procedure within 2 business days after 
  310  such notice: 
  311         1. Any amounts resolved in the contractor’s favor bear 
  312  mandatory interest, as set forth in s. 218.735(10), from the 
  313  date the payment request or invoice containing the disputed 
  314  amounts was submitted to the local governmental entity. 
  315         2. The objection to the payment request or invoice is 
  316  deemed waived. The waiver of such objection does not relieve a 
  317  contractor of its contractual obligations. 
  318         (3) In an action to recover amounts due under this part ss. 
  319  218.70-218.80, the court shall award court costs and reasonable 
  320  attorney’s fees, including fees incurred through any appeal, to 
  321  the prevailing party, if the court finds that the nonprevailing 
  322  party withheld any portion of the payment that is the subject of 
  323  the action without any reasonable basis in law or fact to 
  324  dispute the prevailing party’s claim to those amounts. This 
  325  subsection does not apply to any litigation commenced before 
  326  October 1, 2010. 
  327         Section 4. This act shall take effect October 1, 2010. 